Engineering Economics MCQs

1. Engineering economics is concerned primarily with:

A) Maximizing profits
B) Minimizing costs
C) Evaluating economic alternatives
D) Forecasting future trends

Answer: C) Evaluating economic alternatives

2. The time value of money concept is based on the idea that:

A) Money depreciates over time
B) Money has different values at different times
C) Money is always worth more in the future
D) Money is a constant value

Answer: B) Money has different values at different times

3. Which of the following is not a characteristic of a good economic decision?

A) Considers only initial costs
B) Considers all relevant costs and benefits
C) Considers the time value of money
D) Considers risk and uncertainty

Answer: A) Considers only initial costs

4. Net Present Value (NPV) is used to:

A) Compare projects of different sizes
B) Evaluate the profitability of a project
C) Calculate the payback period
D) Assess project risks

Answer: B) Evaluate the profitability of a project

5. The payback period method:

A) Ignores the time value of money
B) Always selects the project with the highest NPV
C) Considers only profitability
D) Requires complex calculations

Answer: A) Ignores the time value of money

6. The Internal Rate of Return (IRR) is:

A) The discount rate that makes NPV zero
B) The same as the return on investment (ROI)
C) Used only for small projects
D) Always higher than the cost of capital

Answer: A) The discount rate that makes NPV zero

7. In capital budgeting, the term ‘sunk costs’ refers to costs that:

A) Are not recoverable
B) Are incurred in the future
C) Are used to finance the project
D) Are variable in nature

Answer: A) Are not recoverable

8. Which of the following is a disadvantage of the payback period method?

A) Ignores cash flows after payback
B) Requires complex calculations
C) Accounts for time value of money
D) Suitable for all types of projects

Answer: A) Ignores cash flows after payback

9. Economic life of an asset is the:

A) Maximum period until the asset is fully depreciated
B) Minimum period required for payback
C) Time period over which the asset generates revenue
D) Period after which the asset becomes obsolete

Answer: C) Time period over which the asset generates revenue

10. Which of the following factors affect the interest rate in a market economy?

A) Government regulations only
B) Inflation and risk
C) International trade policies
D) Capital budgeting decisions

Answer: B) Inflation and risk

11. In the context of engineering economics, depreciation is:

A) An expense that decreases taxable income
B) An increase in the value of assets over time
C) Only applicable to tangible assets
D) A non-cash expense

Answer: A) An expense that decreases taxable income

12. Which method of depreciation allocates an equal amount of depreciation expense to each year of an asset’s useful life?

A) Straight-line method
B) Double-declining balance method
C) Units of production method
D) Sum-of-the-years’-digits method

Answer: A) Straight-line method

13. The salvage value of an asset is:

A) The initial cost of the asset
B) The book value at the end of its useful life
C) The amount received when the asset is sold or disposed of
D) The annual depreciation expense

Answer: C) The amount received when the asset is sold or disposed of

14. Which of the following is not considered a cash flow in capital budgeting analysis?

A) Initial investment
B) Salvage value
C) Depreciation expense
D) Operating expenses

Answer: C) Depreciation expense

15. A project with a positive Net Present Value (NPV) indicates that:

A) The project should be rejected
B) The project’s benefits exceed its costs
C) The payback period is short
D) The Internal Rate of Return (IRR) is low

Answer: B) The project’s benefits exceed its costs

16. Which of the following is a characteristic of the Modified Internal Rate of Return (MIRR)?

A) It considers only cash flows up to the payback period
B) It is always lower than the Internal Rate of Return (IRR)
C) It assumes reinvestment at the project’s cost of capital
D) It is suitable for projects with equal cash flows

Answer: C) It assumes reinvestment at the project’s cost of capital

17. An annuity is:

A) A one-time lump sum payment
B) A series of equal periodic payments
C) A variable payment based on profits
D) An irregular cash flow pattern

Answer: B) A series of equal periodic payments

18. The Present Worth (PW) method:

A) Calculates the future value of cash flows
B) Discounts future cash flows to the present
C) Ignores the time value of money
D) Compounds interest over time

Answer: B) Discounts future cash flows to the present

19. Which of the following is a limitation of the Payback Period method?

A) Ignores time value of money
B) Requires complex calculations
C) Considers all cash flows
D) Suitable for all types of projects

Answer: A) Ignores time value of money

20. The Economic Order Quantity (EOQ) model is used to determine:

A) The optimal production rate
B) The maximum inventory level
C) The minimum order quantity that minimizes total inventory costs
D) The average demand rate

Answer: C) The minimum order quantity that minimizes total inventory costs

21. Sensitivity analysis in engineering economics is used to:

A) Determine the impact of uncertain variables on project outcomes
B) Calculate the Payback Period
C) Evaluate cash flow patterns
D) Measure project profitability

Answer: A) Determine the impact of uncertain variables on project outcomes

22. In discounted cash flow analysis, the discount rate represents:

A) The inflation rate
B) The cost of capital
C) The project’s return on investment
D) The market interest rate

Answer: B) The cost of capital

23. Which of the following is a method for comparing investment alternatives by converting cash flows to an equivalent annual amount?

A) Net Present Value (NPV)
B) Internal Rate of Return (IRR)
C) Equivalent Annual Cost (EAC)
D) Payback Period

Answer: C) Equivalent Annual Cost (EAC)

24. Which depreciation method allocates a higher depreciation expense in the earlier years of an asset’s life?

A) Straight-line method
B) Sum-of-the-years’-digits method
C) Double-declining balance method
D) Units of production method

Answer: C) Double-declining balance method

More MCQs on Avionics Engineering MCQs

  1. Artificial Intelligence MCQs
  2. Cybersecurity in Avionics MCQs
  3. Spacecraft Avionics MCQs
  4. Unmanned Aerial Vehicles (UAVs) MCQs
  5. Emerging Technologies MCQs
  6. Systems Engineering MCQs
  7. Engineering Economics MCQs
  8. Project Management MCQs
  9. Thermodynamics MCQs
  10. Electromagnetism MCQs
  11. Electromagnetism MCQ
  12. Classical Mechanics MCQs
  13. Modelling and Simulation Techniques MCQs
  14. Aircraft Simulation MCQs
  15. Fault Diagnosis and Management MCQs
  16. Reliability Engineering MCQs
  17. Aircraft Safety Systems MCQs
  18. Aerospace Materials and Composites MCQs
  19. Material Science MCQs
  20. Advanced Control Systems MCQs
  21. Avionics Integration MCQs
  22. Advanced Navigation Systems MCQs
  23. Antenna Theory and Design MCQs
  24. Satellite Communication MCQs
  25. Radio Frequency Communication MCQs
  26. Measurement and Data Acquisition MCQs
  27. Sensor Technologies MCQs
  28. Aircraft Instrumentation MCQs
  29. Communication Signal Processing MCQs
  30. Analog Signal Processing MCQs
  31. Real-Time Systems MCQs
  32. Software Engineering MCQs
  33. Programming Languages (C/C++, Python, etc.) MCQs
  34. Computer Science and Software Engineering MCQs
  35. Instrumentation and Control MCQs
  36. Flight Control Systems MCQs
  37. Control Engineering MCQs
  38. Microprocessors and Microcontrollers MCQs
  39. Electronics and Electrical Engineering MCQs
  40. Radar and Surveillance Systems MCQs
  41. Communication Systems MCQs
  42. Aircraft Navigation Systems MCQs
  43. Avionics System Design MCQs
  44. Aircraft Structures MCQs
  45. Aerodynamics MCQs
  46. Flight Mechanics MCQs
  47. Introduction to Aerospace Engineering MCQs
  48. Aerospace Fundamentals MCQs
  49. Avionics Engineering MCQs

Leave a Comment